ISLAMABAD: CDA has started the process of carpeting the entire main and link roads of ICT including sector I-11, I-14, I-8, I-9, I-10, G, and H series.
According to a news source 10% of work on box # 4 of the sector, I-11 is completed while 25% of work on the sewerage and drainage system has also been completed in I-11. A tender for street # 32 of the said sector is in its final phase.
The remaining development and restoration work on the infrastructure of Sector I-14 is also underway and 95% of work on the drainage system of the said sector is also completed.
35% of the remaining work of the project is in its progress. Development of the streets of the sector has also been completed.
Likewise, 70% carpeting of the roads of the I and H series has competed as well. 75 street of streets of sectors I-10 is being re-carpeted.
اسلام آباد: سی ڈی اے نے سیکٹر I-11 ، I-14 ، I-8 ، I-9 ، I-10 ، G اور H سیریز سمیت آئی سی ٹی کی تمام مین اور لنک سڑکوں پر قالین سازی کا عمل شروع کردیا۔
ایک خبر ذرائع کے مطابق سیکٹر I-11 کے باکس نمبر 4 پر 10٪ کام مکمل ہوچکا ہے جبکہ I-11 میں سیوریج اور نکاسی آب کے نظام پر 25٪ کام بھی مکمل کرلیا گیا ہے۔ مذکورہ سیکٹر کی گلی # 32 کے لئے ایک ٹینڈر آخری مرحلے میں ہے۔
سیکٹر I-14 کے انفراسٹرکچر پر بقیہ ترقیاتی اور بحالی کا کام بھی جاری ہے اور مذکورہ سیکٹر کے نکاسی آب کے نظام پر 95 فیصد کام بھی مکمل ہوچکا ہے۔
اس منصوبے کا 35٪ کام باقی ہے۔ سیکٹر کی سڑکوں کی ترقی بھی مکمل ہوچکی ہے۔
اسی طرح ، I اور H سیریز کی سڑکوں کی 70٪ قالین سازی کا بھی مقابلہ کیا گیا ہے۔ سیکٹر I-10 کی 75 گلیوں کی سڑکوں کو دوبارہ کارپٹ کیا جارہا ہے۔
Recent News

Relief for Construction Sector: FBR to Reasse...
21 Jan 2025

FBR Eliminates New Baggage Rule on Items Wort...
11 Dec 2024

FBR Eliminates Holding Period for Property Ca...
02 Aug 2024

LDA Auction 2024: Investment Opportunity in F...
10 May 2024